May

Day Project Second priority Notes
1 mm-VLBI SIS tests/maintenance
2 mm-VLBI SIS tests/maintenance
3 mm-VLBI SIS tests/maintenance
4 mm-VLBI GMVA session
5 mm-VLBI GMVA session
6 mm-VLBI GMVA session
7 mm-VLBI GMVA session
8 mm-VLBI GMVA session
9 mm-VLBI GMVA session
10 mm-VLBI GMVA session
11 mm-VLBI ?
12 mm-VLBI QSO/GIX ?
13 QSO/GIX
14 QSO/GIX
15 QSO/GIX
16 QSO/GIX
17 QSO/GIX
18 Ava RFI QSO/GIX RFI source operating during daytime! (Exact time TBD)
19 Ava RFI? QSO/GIX RFI source possibly operating during daytime!
20 QSO/GIX
21 QSO/GIX
22 S-band SMART-1 (Ari & Jouko) rx change to 2/8 GHz VLBI
23 S-band SMART-1 (Ari & Jouko)
24 S-band SMART-1 (Ari & Jouko)
25 S-band SMART-1 (Ari & Jouko) Helatorstai
26 S-band SMART-1 (Ari & Jouko)
27 Geo-VLBI
28 Geo-VLBI
29 Geo-VLBI Actual geo session UT 12-->
30 Geo-VLBI
31 Geo-VLBI QSO/GIX Rx change 2/8 GHz VLBI --> 22/37 GHz cont