Day Project Second priority Notes
1 Geo-VLBI QSO/GIX Rx change cont --> S/X VLBI
2 Geo-VLBI   Session starts at UTC 17:30
3 Geo-VLBI   Geo session ends at UTC 17:30
4 Geo-VLBI Guifré / VEX  
5 Guifré / VEX QSO/GIX Rx change S/X VLBI --> cont
6 QSO/GIX
7 QSO/GIX
8 Maintenance / 3 mm rx tests   Rx change continuum to new 3mm VLBI
9 Maintenance / 3 mm rx tests    
10 Maintenance / 3 mm rx tests QSO/GIX  
11 Maintenance / 3 mm rx tests? QSO/GIX  
12 Maintenance / 3 mm rx tests? QSO/GIX Rx change to continuum?
13 QSO/GIX
14 QSO/GIX
15 QSO/GIX
16 QSO/GIX
17 QSO/GIX
18 QSO/GIX
19 QSO/GIX
20 QSO/GIX
21 QSO/GIX
22 QSO/GIX
23 Maintenance / 3 mm rx tests QSO/GIX Rx change continuum to new 3mm VLBI
24 Maintenance / 3 mm rx tests    
25 Maintenance / 3 mm rx tests QSO/GIX  
26 Maintenance / 3 mm rx tests? QSO/GIX Rx change back to 22/37 GHz continuum
at latest today!
27 QSO/GIX
28 QSO/GIX
29 QSO/GIX
30 QSO/GIX
31 QSO/GIX